Manager: We (meaning you) need to do task A. How long will it take?

Me: Task A will take X days to do.

Manager: That seems awful long.

Me: How long do you think it should take?

Manager: It surely could not take any longer than Y days.

Me: Ok, it seems you have an answer to your question then.

Later:

Manager: It’s been Y days, why isn’t task A done yet?

  • zerofk@lemmy.zip
    link
    fedilink
    arrow-up
    5
    ·
    2 hours ago

    I’m really sorry this seems to be so common. I’m in a position where my PM accepts the team’s estimate, and even understands it’s just an estimate.

    • TheDoozer@lemmy.world
      link
      fedilink
      arrow-up
      1
      ·
      28 minutes ago

      I don’t work in programming (helicopter maintenance/repair), but my boss goes one step further.

      Boss: How long until it’s ready for a test flight?

      Me: I’d say…

      Boss: Wait. Give me an honest number, don’t add buffer time. I’m already going to double whatever you say to tell District.

      Me: Oh, okay, with paperwork and ops checks, 3 hours is feasible, as long as we don’t encounter any other issues.

      Boss: roger, six hours, sounds good.